The extension will be connected to the existing hospital. It will provide eight more aged care beds.
Proposed works
- New 8-bed residential aged care unit.
- New kitchen and laundry.
- Existing kitchen converted into a storeroom.
We'll also be adding car parks, and outdoor areas for residents, families, and visitors to use.
The project is part of Queensland Health’s Sustaining Capital Program. The department leads the tendering and contracting of building contractors and consultants of all major health projects.
Timeline
- Start date: Late 2024, early works begin.
- Finish date: Late 2025, weather and building conditions permitting.
Artist impression
Images are a representation only and should not be relied upon as images reflecting the hospital/service/health facility at completion. These images are subject to significant change through the design process which commences upon the appointment of the managing contractor.
Contact us